Greening the grid: That鈥檚 how 乐播传媒 characterizes its latest initiative in the effort to stay sustainable.

The college is partnering with ReVision Energy, a leading solar facilities provider in Maine, to establish a photovoltaic array on more than 20 acres of countryside in the town of Skowhegan. The array will comprise nearly 18,500 panels and feed into the regional grid 7.131 megawatts of direct current, or DC, which will be converted to alternating current, or AC, for grid distribution to businesses and residences.

That鈥檚 about three-quarters of the college鈥檚 electrical usage, says Tom Twist, 乐播传媒鈥 sustainability manager. The array itself will be the largest has built to date, although it鈥檚 working on others of comparable size.

The project is scheduled to begin generation this summer, barring a recurrence of supply chain issues that have affected electrical components in particular.

Completed sections of the new 乐播传媒 solar array in Skowhegan, shown photovoltaic modules on Jan. 24. (Courtesy of ReVision Energy)
Completed sections of the new 乐播传媒 solar array in Skowhegan, shown on Jan. 24. (ReVision Energy photo)

To be clear, 乐播传媒 has met its electrical needs with renewable power since 2005, when the college began sourcing its juice in the form of Renewable Energy Certificates, or RECs, from Maryland-based Constellation Energy. In effect, RECs are documents affirming that a certain amount of power has been generated sustainably. (The college will continue to buy RECs for the roughly 25 percent of its electrical usage not produced by the solar array.)

What the Skowhegan project will change, though, is that 乐播传媒, in partnership with ReVision, will take direct responsibility for creating its own green electricity.

Leased for the solar project by landowner Jim Henshaw, a farmer, the construction site is open land some distance back from Eaton Mountain Road.

鈥淚t鈥檚 kind of hidden and tucked away in there, surrounded by forest,鈥 says Brian Byrne, the ReVision project manager overseeing the construction. (The staff land developer for ReVision who helped put the lease arrangement together is Holly Noyes 鈥10, who is also a farmer.)

In some ways, the site was a solar installer鈥檚 dream. 鈥淚t鈥檚 a nice, beautiful, wide-open field. We didn’t have to clear any trees,鈥 Byrne explains. It鈥檚 heavily vegetated and very well-drained, meaning that there are no wetlands, no areas vulnerable to erosion, and no threat of stormwater runoff or sediment washing off the site. 鈥淔rom a Department of Environmental Protection perspective, this has been the greatest site we’ve ever dealt with.鈥

The 乐播传媒鈥揜eVision Energy solar array site in Skowhegan. (ReVision Energy photo)

Sullying the dream, though, were conditions three or four feet below the soil surface. Typical for a ground-level PV array, the 乐播传媒 project consists of long rows of solar panels, aka modules, attached to 鈥渞acks鈥 鈥 horizontal rails mounted on steel piles that are driven into the earth. So pile driving was the first order of business when construction began last summer. And cue the tension-building music:

鈥淲e thought this was just going to be a very deep soil, like a sandy loam,鈥 says Byrne, 鈥渂ut it’s actually incredibly compact, dense clay when you hit about three feet鈥 below the surface, punctuated with boulders. (Marine clay strikes again!)

As is its wont, the clay all but stalled progress. 鈥淭his site appeared to be a dream from the surface,鈥 says Byrne, 鈥渂ut once we started driving these steel piles, which support the racking, we could not drive them in.鈥 Between the clay and the underground boulders, fully half of the 2,500 piles couldn鈥檛 be driven to the depth necessary 鈥 below the frost line, more than six feet under.

鈥淭o make matters worse, we could not pull them back out because it was such compacted clay. The amount of force [necessary] was unbelievable. It just seemed to defy physics,鈥 Byrne says. 鈥淪o we had to dig them out.鈥

In the end, Gardiner-based Maine Drilling & Blasting came in to pre-drill holes for the undrivable half of the piles, which are 16-foot steel I-beams. 

The solar array occupies some 20 acres of open land enclosed by woods. (ReVision Energy photo)

鈥淚n our ideal world, we wanted all of the modules to be mounted to the racking by the end of December, and that did not happen because the racking was so delayed.鈥

For the sake of context, the company fabricating and placing the racks, RBI Solar of Cincinnati, 鈥渨as anticipating 12 to 14 weeks to complete this project.鈥 Now completing final punch list items, 鈥渢hey鈥檙e on week 26.鈥

鈥淭his was the greatest delay we鈥檝e ever encountered for installing racking,鈥 Byrne says.

Which is not to say that the trials of the piles stalled the project outright. 鈥淚f there’s an obstacle, we move around it and keep pushing forward,鈥 says Byrne. 鈥淲hile we were delayed with racking, there were other things to do.鈥 In conjunction with a regular business partner, Gifford Electric of Brewer, Maine, the project team installed utility poles, equipment racks, DC combiners and transformers; dug trenches for electric lines; and pulled conduits.

As this was written, about 60 percent of the 18,486 modules were in place. Two types of solar modules, one slightly more powerful than the other, are being used. Rated at 395 watts is a model made by the German company Qcells: 7,098 of those will be installed. REC Solar produces the other module: 11,388 of those at the 乐播传媒 site will each generate 380 watts.

Empty racks and a temporary storage shed at the Skowhegan  solar array. (ReVision Energy photo)
Empty racks and a temporary storage shed at the Skowhegan solar array. (ReVision Energy photo)

(In short, here鈥檚 more about AC/DC, and we鈥檙e not discussing Angus Young鈥檚 stage attire: Sunlight on solar panels generates DC, which is converted to AC for long-distance distribution. The Skowhegan solar plant will inject about 5 MW of AC current into the grid.)

Each type weighs just over 50 pounds apiece and measures about 80 by 40 inches. Byrne explains that installation is a succession of steps performed in waves by just a handful of people 鈥 pre-positioning components, attaching some hardware, placing the lower row of modules, attaching more hardware, placing the upper row of modules.

On average, in benign conditions, a useful rule of thumb is that during a nine-hour day, one installer can mount approximately 75 lower-rack modules or 50 on the upper section.

鈥淓verything is prepared before the crew does the task, and that’s how we can maintain efficiency. It stays very organized, very clean. There’s no garbage blowing around the field.鈥 In fact, Byrne adds, 鈥淪olar is my favorite construction project. It’s not a typical construction site. Once the excavation鈥檚 done and you pound the posts, these are the only silent construction sites there are, and it鈥檚 fantastic.

鈥淚f you can hear the birds, and watch the leaves blow and the grass bend, that’s pretty ideal.鈥

ReVision Energy uses temporary huts like this to protect equipment and supplies from the elements. (ReVision Energy photo)
ReVision Energy uses temporary huts like this to protect equipment and supplies from the elements. (ReVision Energy photo)

Not to mention listening to the munching of sheep on the grass that will continue to grow at the project site. Historically used for hay cutting and on-site grazing, Henshaw鈥檚 land will continue to support haying twice a year, as prescribed by a land-use permit, and grazing any old time.

乐播传媒 and ReVision have worked together for years, one high-profile result being the installation, over two years, of rooftop solar at the 乐播传媒 Coastal Center at Shortridge.

The current (no pun intended, but it鈥檚 not bad) collaboration dates to the years just prior to the pandemic. Driven in part by strong student interest in sourcing 乐播传媒 electricity from large-scale solar, the college undertook a rigorous exploration of its options.

In 2019, the state of Maine enacted legislation that in various ways advanced the cause of renewable energy. One of those bills, L.D. 1711, made financial outcomes 鈥渕uch more fair for large solar electricity customers,鈥 explains Tom Twist, 乐播传媒鈥 sustainability manager.

鈥淎s soon as that was passed, we were able to hit the ground running鈥 in developing a workable model for involvement in a solar farm. That contrasts with a number of other large solar projects in Maine that are still hanging fire, Twist says. 鈥淲e feel really lucky that this is going through.鈥

As a member of the 乐播传媒 EcoReps, students who undertake a variety of campus sustainability projects, economics major Kyung Phil 鈥淜P鈥 Ko 鈥22 was one of several involved with that modeling process. 鈥淲e dug into the proposals sent over by a few parties, ReVision being one of them, to really understand what the benefits to 乐播传媒 would be,鈥 explains Ko, who now analyzes U.S. utilities and power issues for Scotiabank.

Kyung Phil Ko of Toronto, Canada, in his room at Village 1, with his laptop, and in some pictures, with an electrical cord that hooks his laptop to his speakers.

 It soon became clear that three seniors in the course 鈥 Leo Crossman, Fahim Khan, and Avi Brach-Neufeld 鈥 already had considerable know-how in the snake-named programming language. (Also involved in the project are two EcoReps, Biruk Chafamo 鈥22 of Addis Ababa, Ethiopia, and Kyung Phil Ko 鈥22 of Ontario.)
Shown in his 乐播传媒 dorm room in 2020, Kyung Phil Ko 鈥22 of New York City was one of the 乐播传媒 EcoReps who helped the college prepare for its solar-electricity partnership with ReVision Energy. (Phyllis Graber Jensen/乐播传媒 College)

鈥淥nce the benefits were understood, we worked this up the decision-maker chain. To be exact, the arrangement was a financial PPA, where 乐播传媒 could hedge against the volatility of electricity bills thereby bringing us cost savings and monetizable renewable energy credits.鈥

鈥淩eaching construction is a humongous milestone worthy of hoots and holler.鈥

KP Ko 鈥22

鈥淚 can鈥檛 tell you how happy I am that the project has reached the construction stage,鈥 Ko adds. 鈥淲orking in the renewable energy investment banking space, I can tell you that the industry has faced incredible uphill battles over the past year with supply chain issues, inflation, bloated interconnection queues, and what almost was the end of solar investment tax credits.

鈥淩eaching construction is a humongous milestone worthy of hoots and holler. I hope to visit Maine sometime soon and see the arrays for myself.鈥

The work of Ko, his classmate Tamsin Stringer, and other students was invaluable to the project. 鈥淭o figure out the costs, figure out the net value of solar electricity several years into the future 鈥 all those things were complicated, and the students did a really nice job,鈥 says Twist. 鈥淩eally professional-level.鈥

With more than half the solar modules in place, the new array is shown in a drone view. Stacked in the parking area in the foreground are snow-coated pallets of modules and empty pallets. (ReVision Energy photo)

He adds, ReVision 鈥渒nows the ins and outs of the solar market around Maine, and they were really able to help us. I think if we went with someone who wasn’t familiar with Maine, we’d still be stuck.鈥

In sum, when 乐播传媒 saw the opportunity to go solar in a big way, 鈥渨e were ready for it,鈥 says Geoff Swift, the college鈥檚 vice president for finance and administration and treasurer. 鈥淭here were things that had to happen before other things could happen, so it took a long time to get to where we are today.

鈥淏ut it’s thrilling to have the array in process and going up in Skowhegan.鈥

Can we talk? Campus Construction Update wants to hear from you. Please send your comments and questions about construction at 乐播传媒, as well as your feelings about marine clay, to dhubley@bates.edu, with “Campus Construction” or “What do sheep count when they can’t sleep?” in the subject line.